docs: document phase 5b, the server as a project home

Phase 5b had only module rows and the review's DECISIONS and CHANGELOG lines.
The brief now describes the server home as the code does after the review
fixes: the projects API, projectChanged, the capability, the settings PATCH
under the lease, renders of a project version, the panel's Projects section,
and the desktop's server projects (open, copy, sync, chip, renders, viewers).

DECISIONS gains the phase's own rows; the 5b rows are dated 2026-10-26 like
the other review-2 phases, and three 5a rows are marked partly superseded.
CHANGELOG, STATUS, the request's 5b row and ARCHITECTURE follow the code
(frames stamp, stored reads, the .thumb marker, followed renames, the
editor's sign-in).

Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com>
This commit is contained in:
Alby96andClaude Opus 5.5 committed 2026-11-04 13:19:55 +01:00
1 parent ae41c95682
commit 3ade4b8d6c
6 files changed
+258 -62

No files matched your search

+1 -1
View File
@@ -75,7 +75,7 @@
| 4a | R7 Reorganize after import | done 2026-10-27, released as `v0.1.0-rc.6` (one adversarial review round and six fix rounds; strings in all 38 languages): BRIEF §5, §7, §7.1, §12.2, §12.5, §12.8, §13, §14.3, §14.5, §14.8, §24; 25 DECISIONS rows dated 2026-10-26 (R7 one naming rule `FrameNaming` for import, upload and Reorganize; what Reorganize renames and what stays whole; unique names in index order and XMP companions; the two-phase file journal; step order and checks under the leases; the fingerprint pinning file renames by digest; sequences still receiving photos; a sequence left inside a moving folder taken along; Reorganize as the `move` job with held plans; the whole-plan tally and errors; `sequenceChanged` `reorganized` and the editor reload; exports rebased with their folder; the rows of a sequence that took the old folder never follow; writers under the lease and render filing's 503; a folder another sequence holds refused by every writer; proxy lease batches; case-only and stable folders; template rules; rules held only to templates given anew; the server's plan cache; the reorganize API; panel selection and dialog; the desktop dialog and the Settings toast; render leftovers removed only where the sequence is; originals restored only where the sequence is), three earlier rows marked superseded; CHANGELOG [0.1.0-rc.6] with the template upgrade note and the known limitations; STATUS 8.3 | `7e4a3b48` |
| 4b | R7 mass conversion | done 2026-11-02, released as `v0.1.0-rc.7` (one adversarial review round, 42 findings, and two fix rounds; strings in all 38 languages): BRIEF §5, §7, §8.1, §8.3, §8.7, §9, §12.2, §12.4, §12.5, §13, §14.3, §14.4, §14.5, §14.8, §14.9, §24; 26 DECISIONS rows dated 2026-10-26 (R7 conversion after import, import still byte for byte; Replace or New sequence at every run, never remembered; targets and the scene-referred archival DNG; the conversion's decoder order, managed first and no 16-bit file from an 8-bit RAW development; the TIFF reader's refusals; colour profiles carried, converted or refused; the converted files' Exif; a dry run that probes what it promises; exactly the confirmed photos, by digest and ids; the two-stage, resumable job; the purge of staging and journals; free space measured where the conversion writes; no conversion of the same sequences twice; New sequence holding the converted copies alone, saying what it lacks; the Replace swap; the replace journal decided by content; Undo by the job's own entries; replaced entries weighed against the archive on disk; every last copy named before the typed confirmation; sync aliases as equivalence classes; link by content, proxies and downloads following them; the ingest taking a replaced original as present; the plan cache shared with Reorganize; the convert API; the `convert` job kind; failure sentences by cause), four earlier rows marked superseded in part; CHANGELOG [0.1.0-rc.7] with the upgrade note and the known limitations; STATUS 8.3 | `efa87f68` |
| 5a | R8 workspace and projects with a local home (migration 0009) | done 2026-11-03, released as `v0.1.0-rc.8` on 2026-11-04 (one adversarial review round, 55 findings, and five fix rounds; strings in en and it, the 36 other languages still to translate): BRIEF §4.4, §5, §7, §12.2, §12.3, §12.6, §12.8, §14.5, §14.6, §24; 46 DECISIONS rows dated 2026-11-03 (R8 projects and versions in the index by migration 0009; the sidecars as the truth; the portable form with positions parked by photo and canonical text; placing by photo; unknown members kept; a newer settings format read only; project file format 2; the 64 MiB limits; Main mirroring the settings and `project.json`; the Main catch-up merge; a mirror never written over settings it has not taken in; deletion from the trash read first, late versions moved beside it; lost and behind records; one Main; push rules; `IProjectHome`; the workspace folder and its write order; versions set aside and pruned; conflicts and Save both naming; media learning names; the frames stamp; Gone and Damaged states; newer and damaged copies; Edit opening workspace projects; editor saves; sync; Kept versions; Remove local copy; Delete project; the workspace copy job and its cancel clean-up; renders with project and version; `.chronos` files; the picker; Settings › Workspace; texts; `IWorkspaceUi`; leases), five earlier rows marked superseded in part; CHANGELOG [0.1.0-rc.8] with the migration 0009 upgrade note and the known limitations; STATUS 8.3 | `9b24cf74` |
| 5b | R8 server home | todo | |
| 5b | R8 server home | done 2026-11-04, to be released as `v0.1.0-rc.10` (one adversarial review round, 21 findings, 19 fixed; strings in en and it, the 36 other languages still to translate; the Server screen's row buttons and the TEMP path in 8 screenshot baselines still open): BRIEF §4.4, §7, §12.2, §12.3, §12.7, §14.3, §14.5, §14.7, §14.8, §24; 40 DECISIONS rows dated 2026-10-26 (R8 the server home on the archive's `ProjectService`, errors mapped to Offline, refusals and API errors; a deleted project's head 404; `too_large` and `projects_unreadable`; change sets told after the lease; pruning by read-back; the copy from a server; texts of the server; renders of what the server holds; Edit opening server sequences; 404 `not_found` with details; push results; the pushing account as author; numbered version pages; delete rights and Main's rename; `sequenceChanged` with Main's mirror; `ProjectCatchUp`; events to every subscriber; render jobs and nodes of a project version; the `projects` capability; the frames answer; the panel's Projects section; `HomePhotos` public; the sign-in as the only way to a server home; the server's archive id; the copy's download and metered rule; `ServerJobs`; the older server's disabled action; review fixes: the frames stamp, sequences without photos, the settings `PATCH` under the lease, push and page size limits, the maker's account, rescans and read-only catch-ups told, missed changes told once the stream is back, server renames followed, the stored check, the `.thumb` marker, viewers with proxies, the editor following the sign-in), three earlier rows marked superseded in part; CHANGELOG [Unreleased] with the upgrade note and the known limitations; STATUS 8.3 | |
| 5c | R8 originals, local render, clean-up, Workspace settings | todo | |